What is HVDC and what are the benefits?

TenneT is building two transformer platforms in the IJmuiden Ver wind energy area that convert the alternating current from offshore wind energy into direct current. A first in the Netherlands. High Voltage Direct Current (HVDC): direct current with high voltage is used to transport power. Over long distances, HVDC has relatively fewer losses than alternating current (AC) systems. Yet the choice for HVDC is not just an obvious one.

Origin

Sea cables for electricity have been around for a long time. A number of the Wadden Islands and many other islands and wind farms worldwide are connected to the electricity grid by sea cables. Cables that use direct current are also not new.

Heavy HVDC cables are a fairly new phenomenon compared to the traditionally used AC high voltage. They are often used for submarine connections to transport electricity internationally and to connect supply and demand of countries, where this was previously not possible because there was a sea in between. They have become indispensable in the net.

Marine cables capable of transporting the total power of a large power plant are a relatively new phenomenon. This is because it is technically complicated to convert power from alternating current to direct current and then changing it back to alternating current at the other end of the cable.

The first of the new generation of high-capacity HVDC interconnectors is the Baltic Cable (Germany-Sweden), delivered in 1991.

Developments

Since that year, developments in cable technology and conversion stations have been rapid on both sides. About thirty HVDC cables are currently running through the European seabed (and partly above ground).

In the Netherlands, the NorNed cable , between the Netherlands and Norway, was completed in 2008. This connection has a capacity of 700 MW and is currently the longest submarine power cable in the world.

The BritNed cable was also completed in 2010, with a slightly higher capacity (1000 MVA). A third connection is currently under construction, the COBRA Cable (between Eemshaven and Endrup).

HVDC-station - Siemens Energy

Comparison

Alternating Current (AC), or alternating voltage, differs from Direct Current (DC) direct current because with alternating voltage the current constantly changes direction.

Overall, alternating current has higher costs per kilometer and lower costs for the stations on either side. With a high-voltage DC grid it is the other way around: there are higher costs for more complex on- and offshore converter stations and lower costs per kilometer. How exactly does that work?

HVDC-system with convertor stations at sea and on land - Source: TenneT
Projects HVDC - Source: TenneT

Into practice

Although the choice for HVDC is especially obvious for longer distances, it requires quite a bit of investment from grid operators. Also in other areas, such as knowledge development and the much more complex logistics processes.

Work is now underway on the construction of HVDC systems in various places, such as for IJmuiden Ver.

To bring the ever-increasing yield of wind energy onshore, TenneT and its partners will build at least 14 high-voltage direct current (HVDC) offshore grid connection systems by 2032, each with a transport capacity of 2 gigawatts (GW) in the Dutch and German North Sea. Once implemented, they will supply up to 35 million households with green wind energy from the North Sea.

The future also seems to point in the direction of HVDC in a European context. The European grid can be connected into a much more effective network in which different geographical areas can make much more efficient use of existing and renewable production and shifting use.

Preparations for the retraction of the 1st submarine cable off the Dutch Coast (west Bèta) - Source: TenneT

New planning

On April 28, 2024, outgoing Minister Jetten sent the additions to the offshore wind roadmap to Parliament. This includes an adjusted schedule for the completion of a number of lots and tenders. As a result of the longer period for connecting the wind farms to the TenneT platforms and as a result of delays in the delivery of some platforms, the dates for commissioning the wind farms are shifting.

Bekijk al het nieuws

Discover the benefits of the NedZero Membership

More information

Together with our members, we strive for a strong wind sector and the necessary new policy for a green future.

Arthur van Schendelstraat 600
3511 MJ Utrecht

Contact
Newsletter

Keep up to date with the latest news:

Subscribe
Follow us
Privacy Clearance Disclaimer